A Chandelier About To Be Lowered The electrical works to rewire the church at Great Badminton, which was the aim of Phase 1 of the Restoration project, were completed on Ash Wednesday (1st March) 2017. Although the bulk of the disruptive works were completed in November, there have been plenty of smaller tasks, many of them in areas of the church …
Phase 1 To Rewire and Heat the Church Commences
We are pleased to announce that we are in a position to start work on Phase 1 of The Great Badminton Church Restoration Fund project, to rewire the entire building and heat the church, in mid-October 2016. The work will primarily involve electrical works of all sorts. Rewiring of the entire church. Replacing its fuse boxes and distribution boards with …